OVA ENERGY INC.
Date of Establishment | : 21.08.2015 | |
Project Name | : Ova Hydroelectric Power Plant | |
Commissioning Date | : 25.09.2019 | |
Location | : Sakarya / Pamukova | |
Installed Capacity | : 13,5 MW | |
Subject of Activity | : Renewable / Hydraulic / Canal Type | |
Objective |
:Ova HEPP project, which was implemented with an investment of 47 million dollars, produces an average of 42 million kWh of electricity annually, meeting all the electricity needs of 14.000 people and reducing a total of 24.000 tons of CO2. In other words, we prevent carbon emissions for nature equivalent to planting 58.000 new trees each year. |
Dr. Zeynel Abidin ERDEM
Dr. Mehmet Nezih ERDEM
Mehmet Rıza ERDEM
Renewable Energy: Installation and operation of hydro power plants.